Edinburgh Tram Line Work Could See 18 Months Of Disruption To Leith Walk

29 August 2017, 11:40 | Updated: 29 August 2017, 11:42

Edinburgh

One of Edinburgh's busiest thoroughfares will face 18 months of disruption if an extension to the city's tram line goes ahead.

A fresh business case for extending the line 4.6km (2.8 miles) from York Place to Newhaven sets out plans to close three lanes of Leith Walk over the period.

A compensation and support scheme would be set up for businesses along the route, many of which have expressed concerns about the impact of the project.

The new report puts the cost of the scheme at £165.2 million based on construction work starting in 2019 and services running on the line by spring 2022.

It estimates the extended tram line will have a positive economic impact on the city, with every £1 spent providing a return of £1.64.

The council approved in principle the option of completing the existing tram line to Newhaven in December 2015.

The report will now be considered at a special meeting of the local authority's transport and environment committee on September 4 before going to full council on September 21.

It seeks authority to begin identifying a potential contractor for the project, with a final decision on whether to go ahead to follow in autumn 2018.

Council leader Adam McVey said: "Edinburgh is growing faster than any other city in Scotland and our current road network and public transport provision simply aren't sustainable given the number of new residents we're expecting to welcome here over the next two decades.

"Rather than exacerbating traffic problems on our already-congested roads, trams allow far greater numbers of people to travel while creating employment during construction, boosting development along the route and connecting people to centres of employment, leisure and retail."

The consideration of the business case will coincide with public hearings in the inquiry into the original Edinburgh trams scheme.

The probe, set up in 2014 by the then first minister Alex Salmond and led by Lord Hardie, is examining why the project went significantly over budget and was delivered years later than originally planned.

The new business case suggests that a process is put in place to ensure all recommendations from the inquiry are taken into account before contracts for the new construction works are signed.

Transport convener councillor Lesley Macinnes said: "Given the experience of the last tram project, we're acutely aware of the need to scrutinise this business case as rigorously as we possibly can - residents deserve nothing less.

"We won't take any decision on completing the line to Newhaven until we are 100% confident that the project can be delivered, financed and managed effectively."